Securing the SwePol Link

NKT cable systems enable high-voltage power transmission between Sweden and Poland and pave the way for new investments in power generation.

Key Facts

Client

SwePol Link

Total cable route length

250 km

Location of the project

The Baltic Sea

Duration

1999 - 2000

Quantity of order

A turnkey 450 kV (kilovolt) HVDC submarine and underground cable system with a capacity of 600 MW (megawatt)

Scope

SwePol Link
SwePol Link
SwePol Link

The project

The aim of the SwePol Link between Sweden and Poland is to strengthen power transmission and power exchange in Europe as well as to enable a continuous development of green and efficient solutions.

The solution

We designed, manufactured, laid, protected the cable at sea and provided all installation for land.